Sports

May 16, 2012

Target for tennis center repair: August

More articles by »
Written by: admin
Tags:
DSC0805

Two of the four construction workers on site, bridging the steal structure during the week.

T

he $2.1 reconstruction project of the tennis center has faced minor delays and is expected to be ready for use in August instead of the original plan of having it done by June.

The center was destroyed in the September 2010 tornado that hit Queens College and left only debris and a fragile bubble’s structure behind.

When construction began early this year, the scheduled date of completions was set for June 2012 but Wing Chan, QC’s project manager, hoped to have it finished by April.

“There are some technical things they had to overcome. One of the things was condensation issues that contractor and designers had to take care of,” Chan said.

Physical work on the court started on April 28 with only a crew of four to six people who have started replacing the brazing, which is bridging or joining the steel beams.

Chan explained the safety issue of many crew members’ mobility on the floor and on the higher parts of the beam that can cause injuries or slow down the project’s process.

The small crew works on a daily basis to catch up for time lost. They pace themselves in cue for the bubble’s fabric, which will be shipped from Japan and arrive in early or mid-July.

After the fabric is placed, the last aspect of this contract’s construction will be the partition of the courts and the new air curtain at the entrance. The structure is designed to look the same as the previous one.

Within the structure some parts of the courts were damaged by the debris.

“I’m not happy with the sample patching,” Chan said. “When you play, if the court is the same the friction is the same but the new patch has a different feel.”

Chan hopes to have the entire court repaired but this repair is not part of the original contract. He will wait for the completion of the current contract to see if there is a need and budget to start court repairs, which he said costs a couple of hundred thousand dollars. According to Chan, this would not take longer than a couple of days, and would not have an effect on the targeted finish date.



About the Author

admin





Advertisement
 
 

 
track team

Knights Men’s Track and Field Win ECC Championship

The Knights Men’s Track and Field team won the inaugural East Coast Conference Outdoor Championship on May 5. The event was close and came down to the final two races on day two at Queens College, but the Knights held off St....
by Michael Florio
0

 
 
donation

CUNY Receives Huge Sum

The City University of New York received a $25 million donation from the Stella and Charles Guttman Foundation on May 1 as part of an effort to boost graduation and student retention rates. In light of the generous donation, th...
by Isioma Ononye
0

 
 
wage rates

Graduates Hopes For Employment

While the U.S. unemployment rate slipped down from 7.6 to 7.5 percent last month, more than 40 percent of recent college graduates are underemployed according a poll released on April 30. The survey of 2,060 recent graduates an...
by Aliza Chasan
0

 

 
Picture1

CUNY reverses decision to penalize pregnant student

Pregnant college students no longer have to worry about facing forced maternity leave from classes. Stephanie Davis, a Borough of Manhattan Community College student, made headlines several weeks ago when she was told she would...
by Manny Valdez
0

 
Advertisement
 
stopandfrisk

As Stop and Frisk Trial Continues, New Report Details Impact of Marijuana Arrests

“Bogus.” Bogus is the word the New York Police Department used in response to the numerous studies and reports that Queens College sociologist Harry Levine has made. His recent report, “One Million Police Hours: M...
by Brandon Jordan
0

 




Advertisement

Leave a Reply

Your email address will not be published. Required fields are marked *

*

HTML tags are not allowed.


Advertisement